Announcement of power infrastructure maintenance plan at Viettel Ho Chi Minh Data Center in April 2023.

Support Portal  »  Announcements  »  Viewing Article

  Print

Dear Customer,

 

vHost would like to thank you for always trusting and accompanying vHost during the past time.

 

According to the notice that vHost received from Datacenter partner Viettel Ho Chi Minh, vHost would like to send you a plan to maintain the power infrastructure from Viettel partner:

 

State 1:

Start time: From 22h00 on 17/04/2023.
End time: Until  04h00 on 18/04/2023.
Reason:: Running generators with periodic load at Ho Chi Minh Data Center
Impact: None.

State 2:

Start time: From 22h00 on 19/04/2023.
End time: Until  04h00 on 20/04/2023.
Reason:: Running generators with periodic load at Ho Chi Minh Data Center
Impact: None.

State 3:

Start time: From 22h00 on 24/04/2023.
End time: Until  04h00 on 25/04/2023.
Reason:: Running generators with periodic load at Ho Chi Minh Data Center
Impact: None.

State 4:

Start time: From 22h00 on 26/04/2023.
End time: Until  04h00 on 27/04/2023.
Reason:: Running generators with periodic load at Ho Chi Minh Data Center
Impact: None.

 

Note: the above time is the estimated time, the maintenance may be completed earlier than expected

 

To avoid affecting your services, vHost will closely monitor during the infrastructure planning period.

 

If you need further assistance or information, please reply to this email or contact us via below channels:


Share via
Did you find this article useful?  

Related Articles


Comments

Add Comment

Replying to  

CAPTCHA
© vHost.vn